Build Dates

house frame

Landmark dates throughout our build

Metricon Deposit Paid – 14 Oct 2009
Land Exchanged – 30 Oct 2009
Old Home Sold – 27 Nov 2009
Home Contract Signed – 30 Nov 2009
External Colour Selections – 30 Nov 2009
Developer Submittal – 21 Dec 2009
Developer Approval – 24 Dec 2009
Council Submittal – 5 Jan 2010
Interior Colour Selections – 25 Jan 2010
Electrical Appointment – 25 Jan 2010
Council Approval – 11 Mar 2010
Peg Out – 27 Mar 2010
Site Scrape – 8 Apr 2010
Piers Poured – 9 Apr 2010
Slab Poured – 16 Apr 2010
1st Floor Framed – 01 May 2010
2nd Floor Framed -08 May 2010
Plumbing & Windows Installed -15 May 2010
Bricking Started – 19 May 2010
Scaffolding Installed – 21 June 2010
Bricking Finished – 23 June 2010
Guttering & Fascia Installed – 25 June 2010
Main Colorbond Roof Installed – 1 July 2010
Bricks Cleaned – 2 July 2010
Cladded Areas Wrapped – 18 July 2010
Cladding Installed (3 Walls) – 24 July 2010
Garage Roof Installed – 31 July 2010
Outdoor Room Roof Installed – 2 August 2010
Electrical Installed – 3 August 2010
Exterior Doorframes Installed – 4 August 2010
Weatherboard Cladding Completed – 9 August 2010
Fireplace Installed 11 August 2010
Downpipes Installed 12 August 2010
Gyprock Started – 13 August 2010
Gyprock Completed – 16 August 2010
Stairs Installed – 17 August 2010
Internal Doors Installed – 18 August 2010
Exterior Doors Installed – 20 August 2010
Waterproofing Completed – 21 August 2010
Cornices & Skirting Installed – 25 August 2010
Cupboards Installed – 27 August 2010
Wet Area Tiling Completed – 14 September 2010
Painting Completed – 19 September 2010
Garage Door Installed – 23 September 2010
PCI – 21 October 2010
Handover – 1 November 2010